vol.83 número199Caracterización de un residuo de construcción y demolición para la obtención de Ca y Si mediante tratamiento con ácido cítricoComportamiento magnético y estructural del sistema La1.5-xBa1.5+x-yCa yCu3Oz 0.2 ≤ x ≤ 0.4 y 0.3≤ y ≤0.5 índice de autoresíndice de materiabúsqueda de artículos
Home Pagelista alfabética de revistas  

Servicios Personalizados

Revista

Articulo

Indicadores

Links relacionados

  • En proceso de indezaciónCitado por Google
  • No hay articulos similaresSimilares en SciELO
  • En proceso de indezaciónSimilares en Google

Compartir


DYNA

versión impresa ISSN 0012-7353

Resumen

ALVARADO, Yezid A.; PEREZ-GOMEZ, María Isabel; CASTELLANOS-REYES, John Alexis  y  GASCH, Isabel. Technical and economic study of striking and clearing operations in buildings under construction.: Case study in Bogotá, Colombia. Dyna rev.fac.nac.minas [online]. 2016, vol.83, n.199, pp.102-107. ISSN 0012-7353.  https://doi.org/10.15446/dyna.v83n199.56086.

This paper evaluates the economic benefits of shorter construction times that can be attained by applying the New Simplified Procedure (NSP) in multi-storey buildings. The reference building was a multi-storey residential reinforced concrete framework structure with one-way slabs located in Bogotá, Colombia. The study was divided into different phases including the characterization of the components, a study of the different methods to determine load transmissions between slabs and shores, and a review of the cost of renting shoring and formwork materials and labor costs for the building under study. After applying the procedure, an economic assessment was carried out on the execution times obtained in each of the operations studied. The analysis of the construction process of the building structure using the NSP showed that considerable savings can be achieved in construction times without any risk for the integrity of the structure.

Palabras clave : New Simplified Procedure; shores; time estimations; load estimations; estimation of personnel and equipment costs.